During custom small appliance development, buyers may receive T0, T1 or T2 samples after the production molds are completed. These names describe different mold-trial rounds, but they do not automatically indicate that a sample has passed inspection.
The important question is not simply whether a sample is called T0, T1 or T2. It is whether the issues found in the previous round have been corrected and whether the product meets the agreed approval criteria.
At Chaozhou Tongheng Technology Co., Ltd., these samples are used to control mold correction, product verification and production approval for products such as portable fans, desktop fans, humidifiers and aroma diffusers.
For an introduction to the first formal mold trial, read What Is a T0 Sample in Plastic Injection Molding?.
| Sample Stage | Main Purpose | Typical Product Status | Buyer’s Main Decision |
|---|---|---|---|
| T0 | Identify problems in the first formal mold trial | The mold, dimensions, appearance or assembly may still require correction | Confirm the issue list and correction direction |
| T1 | Verify the first round of corrections | Major T0 issues should be improved or closed | Check whether the agreed corrections are effective |
| T2 | Recheck remaining issues and confirm the final condition | The product should be close to the approved production standard | Approve the final sample or request further correction |
The exact naming practice may vary between manufacturers and projects. Some products can be approved after T1, while others may require T2 or an additional trial. Reaching T2 does not automatically mean that the product is ready for mass production.
T0 is the first set of parts produced from the formal production mold. Its main purpose is to reveal actual molding, dimensional and assembly issues.
Typical checks include mold filling, flash, warpage, sink marks, key dimensions, housing fit, component assembly, visible gaps and basic product operation.
The normal T0 decision is not “approved for production.” It is confirmation of:
The issues that must be corrected
The parts or mold areas involved
The proposed correction method
The items that must be checked again at T1
If the buyer wants to change an already approved shape, dimension or function at this stage, it should be identified separately as a new design change rather than a normal T0 correction.
T1 is produced after the agreed T0 corrections have been completed. The review should focus on whether each recorded issue has been solved.
The factory and buyer should check whether:
Each T0 issue is closed, improved or still requires correction
Molded parts, appearance, fit, assembly and functions meet the agreed requirements
The corrections have created any new problems
If T1 meets the agreed criteria, the project may move into final verification and production preparation without a separate T2 trial. If important issues remain, another correction and sample round will be required.
T2 is normally used when issues remain after T1 or when the project requires another formal verification before production approval.
The factory and buyer should confirm that:
Remaining T1 issues have been closed
The corrected parts and final assembly match the approved specification
Material, color, logo and surface finish are correct when included in the sample scope
Product functions and required tests meet the agreed criteria
No new critical issue has appeared after the latest correction
A T2 sample only becomes an approved production reference after the buyer and manufacturer complete the required review. The name “T2” alone does not make it a golden sample.
The approval standard should be based on the confirmed product specification rather than a general impression that the sample “looks acceptable.”
| Approval Area | Typical Approval Criteria |
| Molded parts | No unacceptable short shots, flash, warpage, sink marks or surface defects |
| Key dimensions | Important dimensions and assembly tolerances meet the confirmed requirements |
| Fit and assembly | Housings, fasteners, buttons and internal components fit correctly |
| Appearance | Color, finish, gaps, steps, logo position and visible surfaces are acceptable |
| Function | All confirmed functions operate correctly |
| Reliability | Required performance and reliability checks for the current stage are completed |
| Safety structure | Protective features, insulation, battery location and other applicable safety details follow the approved design |
| Final documents | Sample condition, BOM, drawings and product specification are consistent |
Approval details should reflect the product. A portable fan may require checks for blade clearance, airflow, noise, charging and speed control, while a humidifier may require checks for sealing, atomization and water-shortage protection.
| Result | Meaning | Next Step |
| Approved | The sample meets the agreed requirements | Proceed to production preparation and final sample control |
| Conditionally Approved | Only defined minor items remain and they do not affect function, safety or production | Complete the listed actions and provide the agreed verification evidence |
| Correction Required | Important molding, dimensional, appearance, functional or safety issues remain | Correct the issue and submit another sample for review |
“Conditionally approved” should not be used for unresolved safety, functional or critical assembly problems.
Buyers can use the following format when reviewing T0, T1 or T2 samples:
| Part or Area | Issue Found | Required Result | Priority | Factory Action | Recheck Result | Status |
| Critical / Major / Minor | Open / Closed | |||||
| Critical / Major / Minor | Open / Closed | |||||
| Critical / Major / Minor | Open / Closed |
Clear feedback is more useful than comments such as “please improve the sample.” Mark the location, describe the issue and state the expected result whenever possible.
Before mass production begins, the following items should normally be confirmed:
| Production Approval Item | Confirmation |
| T0/T1/T2 issue list | All critical and major issues are closed |
| Final sample | Approved and retained as the production reference or golden sample |
| Product specification | Final functions, dimensions, materials and appearance are confirmed |
| Production documents | BOM, drawings, assembly requirements and inspection standards are aligned |
| Logo and packaging | Artwork, labels, manuals and packaging are approved where applicable |
| Quality requirements | Inspection items, testing methods and acceptance criteria are confirmed |
For a clearly defined project, the T1/T2 optimization and production-verification stage normally takes approximately 15 working days. The actual time depends on the correction scope, test results, material availability and buyer feedback speed.
For the complete sequence from product definition to production, see OEM Product Development Timeline to Production.
No. A project may pass after T1, while another may require T2 or an additional trial. The result determines the number of rounds.
Yes, if it meets the agreed criteria and is formally confirmed by both parties. Unresolved issues must be closed first.
Yes, but changes to an approved appearance, dimension or function may add engineering work, mold cost and lead time. They should be separated from manufacturing corrections.
T0, T1 and T2 provide a controlled method for finding problems, verifying corrections and preparing a custom small appliance for production. The number on the sample is only a record of the trial round.
Production approval should be based on closed issues, confirmed functions, acceptable appearance, stable assembly and aligned production documents. This reduces misunderstandings and helps both buyer and manufacturer move toward mass production with a clear standard.
If you are developing a custom fan, humidifier, aroma diffuser or another small appliance, contact Chaozhou Tongheng Technology Co., Ltd. and share your product brief, reference sample or current development status.